Village permitUnlawful to construct, alter or repair any building or structure, or part of one, without a village permit - Bal Harbour Code Sec. 6-26(a)
Small jobsNo permit for general maintenance or repairs under $500 in labour and materials - Sec. 6-28
FeesEngineering permit fees, which expressly cover bulkheads, are 2% of the first $1 million of construction value and 1% above that, minimum $150 - Sec. 6-36
Beach bulkheadsRebuilding or repairing existing groins and bulkheads is allowed subject to all permitting requirements; new bulkheads seaward of the coastal construction control line are banned - Sec. 21-448
Pools near the wallOn Indian Creek and Biscayne Bay lots, pool work within 40 ft of a bulkhead needs engineer-sealed plans approved by the village - Sec. 21-353(b)
County reviewThe Building Department runs concurrent review with Miami-Dade; applicants file the village application, the Miami-Dade municipal permit application and paper and electronic drawings, in person at Village Hall - village Building Permits page
Starting earlyA contractor or owner who starts work without a valid permit is charged $300 or a double permit fee, whichever is greater - Sec. 6-27
Plan review feeA nonrefundable plans processing fee is paid when plans are submitted and credited to the permit if it issues within 180 days; after three submittals, each further resubmittal pays the full processing fee again - Sec. 6-30
County Class I permitMiami-Dade DERM must issue a Class I permit before any work in, on, over or upon tidal waters anywhere in the county, including inside cities - County Code Sec. 24-48(1)(d) and 24-48.1(1)(a)
Short formRebuilding or repairing a seawall at the mean high water line or no more than 18 inches waterward of the existing wall qualifies for a short-form application. It also qualifies where existing primary support piles stick out no more than 14 inches, if the new wall is no more than 18 inches waterward of those piles - Sec. 24-48.2(I)(A)(1)
Who decidesA short-form application limited to seawalls is decided by the Department with no County Commission hearing. Most standard-form applications are now decided by the Director, apart from listed exceptions such as variances - Sec. 24-48.2(I)(B)(1)(iii)-(iv) and (II)(C)(1), as amended by Ord. 25-73 (1 July 2025)
County clockOrd. 25-73 Sec. 8 directs the County to issue a Completeness Summary within 10 calendar days of submission and a final decision on short-form seawall applications within 90 calendar days after that summary. The applicant may waive these limits in writing. The County Mayor reported the timeframes apply from 1 Dec 2025 (report to the Commission dated 17 Apr 2026)
No Class I neededSealing cracks and spalls on the cap or face, repairing pilasters, backfilling behind the wall, and limited riprap or sand-cement bags at the toe (no more than 2 ft out) - Sec. 24-48(3)(b)-(f)
Quick approval insteadRepairing or replacing the cap or the tieback system gets a written expedited administrative authorization, answered within 10 business days, if the contractor submits structurally approved plans from the building authority - Sec. 24-48(4)(f)-(g)
Not a substituteA county permit does not relieve the applicant from obtaining all required federal, state and local permits - Sec. 24-48.5(1)
State (FDEP)No state environmental permit is needed to restore a seawall at its previous location, upland of it, or within 18 inches waterward of it - Fla. Stat. 403.813(1)(e). The exemption does not cover permission to use state-owned submerged lands or local requirements - 403.813(1)
State-owned bottomWork over sovereign submerged lands still needs Board of Trustees permission even when the seawall work is exempt - Fla. Stat. 403.813(1)
Federal (Army Corps)A Department of the Army permit is required for structures or work in or affecting navigable waters, either under a nationwide or regional general permit or an individual permit - 33 CFR 322.3(a)