What are the boat lift rules in Bal Harbour?

No lift-specific rule; structures 8 ft past seawalltemporary awnings only, 8 ft max

Bal Harbour's code does not name boat lifts. Outside the Business district, no dock, wharf or structure of any kind may extend more than 8 feet beyond the seawall or rise more than 3.5 feet above mean high tide, and the only cover allowed with a dock is a temporary boat awning no more than 8 feet above mean high tide.

Source: Village of Bal Harbour Code Sec. 21-359 (Supp. 93; Ord. 169); Miami-Dade Code Secs. 24-48, 24-48.2 (Supp. 136); s. 403.813(1)(s), F.S. (2026); 33 CFR 322.3(a) · Verified 2026-10

The detail

Reach and heightNo dock, wharf or structure of any kind more than 8 feet beyond the seawall or higher than 3.5 feet above mean high tide - Code Sec. 21-359(a)
CoversNo cover with any dock except temporary boat awnings no more than 8 feet above mean high tide - Sec. 21-359(a)
Business districtThese limits do not apply in the Business (B) District - Sec. 21-359(a)
Not in the codeNo boat lift or davit wording found (searched lift, boat lift, davit, hoist)
Boat basins and marinasNew boat basins are prohibited, and marinas or multi-slip docking facilities must use docks reaching water at least four feet deep at mean low tide - Code Sec. 21-436
Engineering permit feeDocks are among the works charged the village engineering permit fee: minimum $150, 2.0% of construction value up to $1,000,000 and 1.0% above - Code Sec. 6-36
GroinsGroins may reach no more than 300 feet seaward of the ocean bulkhead line, and the contractor must file a registered engineer's certificate of compliance with the building inspector - Sec. 21-359(b)
HistorySec. 21-359 comes from Ord. No. 169 (29 June 1974); Sec. 21-436 from Ord. No. 356 (13 November 1990) - Secs. 21-359, 21-436
Miami-Dade CountyAny work in, on or over tidal waters needs a county permit from the Department (DERM). A single-family boat lift, davit or floating dock that protrudes no more than 25% of the waterway width may use the short-form application, as may installing a boat lift or davit on a dock, seawall or bulkhead - Miami-Dade Code Secs. 24-48(1)(d), 24-48.2(I)(A)(2), (8), (20).
State and federalFloating boat lifts and floating vessel platforms that meet s. 403.813(1)(s), F.S. (they float at all times, hold the vessel out of the water, and either sit inside a previously permitted slip or total no more than 500 sq ft - 200 sq ft in Outstanding Florida Waters - beside a qualifying dock or bulkhead) need no state permit; a local government may then ask only for a one-time registration unless the platform is attached to a bulkhead with no dock. Structures in navigable waters otherwise need Army Corps authorization unless exempt or under a general permit - 33 CFR 322.3(a).

Your city's height sheet

The elevation your city requires, the datum it is measured in, and the section of code that says so. One page.

Available for the cities whose rule we have verified and sourced.

Done — it is on the way to your inbox. Not there in a minute? Check your Promotions or Spam folder, and move it to your inbox so the next ones arrive.

The county rule behind this

What applies across Miami-Dade County, and where each city departs from it.

The same question, nearby

The rule changes at the city line, not the county line.

Other questions about Bal Harbour

Twelve signs a seawall is failing

What to look for, where to look for it, and what it means when you find it. Walk your wall in twenty minutes.

A screening sheet for owners, not an engineering inspection.

Done — it is on the way to your inbox. Not there in a minute? Check your Promotions or Spam folder, and move it to your inbox so the next ones arrive.