Surfside ties its seawall height to the FEMA flood map, not to a fixed number. Since Ordinance 23-1734 (14 March 2023), the top of a seawall on Biscayne Bay, Indian Creek or Point Lake must be at or above the base flood elevation on the FIRM, may not exceed the town's minimum design flood elevation, and must be built so at least two more feet can be added later. Code Sec. 90-63.4.
Source: Town of Surfside Code of Ordinances Sec. 90-63 (90-63.1, 90-63.3, 90-63.4), as amended by Ord. No. 23-1734, Sec. 2, 3-14-23 (Municode); Miami-Dade County Code Ch. 24 · Verified 2026-10
The elevation your city requires, the datum it is measured in, and the section of code that says so. One page.
Available for the cities whose rule we have verified and sourced.
Done — it is on the way to your inbox. Not there in a minute? Check your Promotions or Spam folder, and move it to your inbox so the next ones arrive.
What applies across Miami-Dade County, and where each city departs from it.
The rule changes at the city line, not the county line.
What to look for, where to look for it, and what it means when you find it. Walk your wall in twenty minutes.