City permitThe city adopts the Florida Building Code; applications go on a Development Services Department form, and no development may occur until the Building Department issues a building permit - Sunny Isles Beach Code Sec. 265-20(A)
IssuanceThe Chief Building Official issues the permit only if the work meets all codes and any development orders tied to the project and all fees are paid; the permit card is posted at the front of the premises - Sec. 265-20(C)-(D)
Flood zonesDevelopment in a flood hazard area needs a permit from the Floodplain Administrator and the Building Official - Sec. 161-4(A)
Coastal zone VSeawalls and bulkheads allowed only with federal, state or local authorisation and a design professional's analysis showing no harmful diversion of floodwater or wave reflection - Sec. 161-17(G)
Outside agenciesBuilding staff refer projects to outside agencies; Miami-Dade Fire and DERM are the two typically involved - city Building Permits page
Contractor taxThe city's local business tax schedule lists seawall work under the engineering contractor category, $175 - Code Ch. 197 (schedule codified with Sec. 197-20)
County Class I permitMiami-Dade DERM must issue a Class I permit before any work in, on, over or upon tidal waters anywhere in the county, including inside cities - County Code Sec. 24-48(1)(d) and 24-48.1(1)(a)
Short formRebuilding or repairing a seawall at the mean high water line or no more than 18 inches waterward of the existing wall qualifies for a short-form application. It also qualifies where existing primary support piles stick out no more than 14 inches, if the new wall is no more than 18 inches waterward of those piles - Sec. 24-48.2(I)(A)(1)
Who decidesA short-form application limited to seawalls is decided by the Department with no County Commission hearing. Most standard-form applications are now decided by the Director, apart from listed exceptions such as variances - Sec. 24-48.2(I)(B)(1)(iii)-(iv) and (II)(C)(1), as amended by Ord. 25-73 (1 July 2025)
County clockOrd. 25-73 Sec. 8 directs the County to issue a Completeness Summary within 10 calendar days of submission and a final decision on short-form seawall applications within 90 calendar days after that summary. The applicant may waive these limits in writing. The County Mayor reported the timeframes apply from 1 Dec 2025 (report to the Commission dated 17 Apr 2026)
No Class I neededSealing cracks and spalls on the cap or face, repairing pilasters, backfilling behind the wall, and limited riprap or sand-cement bags at the toe (no more than 2 ft out) - Sec. 24-48(3)(b)-(f)
Quick approval insteadRepairing or replacing the cap or the tieback system gets a written expedited administrative authorization, answered within 10 business days, if the contractor submits structurally approved plans from the building authority - Sec. 24-48(4)(f)-(g)
Not a substituteA county permit does not relieve the applicant from obtaining all required federal, state and local permits - Sec. 24-48.5(1)
State (FDEP)No state environmental permit is needed to restore a seawall at its previous location, upland of it, or within 18 inches waterward of it - Fla. Stat. 403.813(1)(e). The exemption does not cover permission to use state-owned submerged lands or local requirements - 403.813(1)
State-owned bottomWork over sovereign submerged lands still needs Board of Trustees permission even when the seawall work is exempt - Fla. Stat. 403.813(1)
Federal (Army Corps)A Department of the Army permit is required for structures or work in or affecting navigable waters, either under a nationwide or regional general permit or an individual permit - 33 CFR 322.3(a)